Mathews Sheridan Roundabout

2014 Roundabout
Project Cost
  • $647,815
Project Specifications:
  • Removal of existing pavement
  • Grading and seeding
  • Removal of existing signal
  • Asphalt pavement
  • Splitter islands and center islands
  • Relocation of storm sewers
  • Application of pavement markings
  • Installation of traffic control signage
  • Coordinating utility relocations
Funding Sources:
  • CMAQ
  • Enhancement Funds
The contract for the Mathews Sheridan Roundabout was awarded to Parella-Pannunzio, Inc. of Youngstown.